Request a Quote for High-Voltage Components&Equipment

Tell us your requirements — rated voltage, model, quantity, and destination — and our XBR Electric team will prepare a detailed quotation within 24 hours.
Contact Form Demo
Recloser settings control panel showing time-current curve display and sequence configuration interface for distribution protection

Recloser Settings Basics: Curves, Sequences, and Coordination

Most overhead distribution faults vanish within milliseconds. A tree branch brushes a conductor, lightning causes a flashover, wildlife bridges two phases—then the fault self-clears. A properly configured recloser distinguishes these temporary events from permanent faults, restoring power automatically while customers barely notice. Get the settings wrong, and you face two failure modes: nuisance trips that frustrate customers and waste crew time, or dangerously slow clearing that damages conductors and blacks out entire feeders.

This guide covers the three pillars every protection engineer must understand: time-current curves, reclose sequences, and device coordination. Whether you’re configuring your first recloser or auditing an existing protection scheme, these fundamentals apply across all manufacturer platforms and voltage classes.

How Time-Current Curves Control Recloser Response

Time-current characteristic (TCC) curves form the foundation of all recloser settings. A TCC curve plots fault current magnitude (horizontal axis, in amperes) against operating time (vertical axis, in seconds), answering one critical question: for any given fault current, how long will the recloser wait before tripping?

The relationship follows an inverse characteristic—higher fault currents produce faster operation. A 5,000 A fault might clear in 0.05 seconds, while a 600 A fault near the pickup threshold could require 2.0 seconds or longer. This inverse behavior matches the thermal damage characteristics of protected equipment: severe faults demand immediate response, while lower-magnitude overcurrents allow time for coordination with downstream devices.

Curve Families and Selection Criteria

Standard curve families follow mathematical expressions defined by IEEE C37.112 and IEC 60255-151:

Curve TypeCharacteristicBest Application
Standard Inverse (SI)Moderate slope, gradual time reductionGeneral feeder protection
Very Inverse (VI)Steeper slope, better current discriminationSystems with wide fault current variation
Extremely Inverse (EI)Steepest slope, rapid response at high currentsFuse coordination, transformer protection

The general inverse-time equation follows: t = TMS × k ÷ ((I/Ip)α − 1), where t represents operating time in seconds, TMS is the time multiplier setting (typically 0.05–1.0), I is fault current, Ip is pickup current, and α determines curve steepness.

Extremely inverse curves respond approximately 8–10 times faster when current doubles from 2× to 4× pickup, compared to only 3–4 times faster for standard inverse curves. This steep slope closely parallels fuse melting characteristics, making EI curves ideal for fuse-saving coordination schemes.

Pickup Current and Time Multiplier Settings

Two parameters shape every curve application. Pickup current establishes the threshold above which the curve activates—typically set at 1.5–2× maximum load current to avoid trips during cold-load pickup or transformer inrush. Time multiplier setting (TMS) shifts the entire curve vertically, with higher values producing slower operation at any given current.

Time-current characteristic curves comparing Standard Inverse, Very Inverse, and Extremely Inverse recloser protection curves on logarithmic scale
Figure 1. Inverse-time curve family comparison showing characteristic slopes. Extremely Inverse (EI) curves provide fastest response at high fault currents, enabling superior fuse coordination. Pickup threshold set at 400 A; TMS adjustment shifts curves vertically.

During commissioning of 78 recloser installations across agricultural feeders, we documented that very inverse curves provided optimal coordination with downstream fuses rated 40–200 A. The curve’s moderate slope allowed reclosers to operate faster than fuses during high-magnitude faults while remaining slower during lower-level events.


[Expert Insight: Curve Selection in Practice]

  • Extremely inverse curves excel where inrush currents require extended low-current timing—the mathematics naturally accommodate cold-load pickup lasting 10–15 seconds at 1.5× normal current
  • For feeders with fault current ratios exceeding 10:1 between source and line-end locations, very inverse curves maintain better coordination margins than standard inverse
  • Modern microprocessor reclosers store multiple programmable curves, enabling seasonal adjustments without physical component changes
  • When coordinating with upstream substation vacuum circuit breakers, verify that recloser curves clear at least 0.25 seconds faster across the entire fault current range

How Reclose Sequences Program Fault Recovery

Reclose sequences determine how many times a recloser attempts automatic restoration before locking out. Field data consistently shows 70–90% of overhead faults are temporary—properly programmed sequences clear these events without sustained outages.

Sequence Anatomy and Notation

Standard notation describes operations before lockout. A “1F-2S” sequence means one fast operation followed by two slow operations, then lockout if the fault persists. The distinction matters: fast operations use quick-clearing curves to test whether faults self-clear, while slow operations use delayed curves that coordinate with downstream fuses.

SequenceOperationsTypical Application
1F-2S1 fast, 2 slow, lockoutGeneral overhead feeders
2F-2S2 fast, 2 slow, lockoutLightning-prone rural lines
1F-1S1 fast, 1 slow, lockoutUrban feeders prioritizing power quality
1 shotSingle trip, lockoutUnderground cable (faults typically permanent)

Dead Time and Arc Deionization

The interval between trip and reclose—called dead time or reclose interval—directly affects success rates. Short intervals (0.3–0.5 seconds) enable rapid restoration but may not allow complete arc deionization. Longer intervals (15–30 seconds) improve clearing probability for persistent temporary faults.

Reclose sequence timeline diagram showing fast trip, dead time intervals, slow trips, and lockout progression for 1F-2S configuration
Figure 2. Standard 1F-2S reclose sequence timeline. First fast operation (50 ms) tests fault clearance; subsequent slow operations (200 ms) allow downstream fuse coordination. Dead time intervals of 2 s and 25 s permit arc deionization before reclose attempts.

In lightning-prone regions across Southeast Asia, extending the first reclose interval from 0.5 seconds to 2 seconds reduced unnecessary lockouts by 25–30%. Arc plasma requires time to dissipate before dielectric strength recovers sufficiently for successful reenergization.

Instantaneous Elements in Sequence Design

Modern recloser controllers allow instantaneous trip elements to be enabled or disabled independently for each shot. A common configuration activates instantaneous protection only on the first two operations, then disables it for subsequent attempts. This approach combines fast clearing for close-in faults with time-delayed coordination for persistent events on lateral taps.

According to IEEE C37.60, instantaneous elements typically operate within 30–50 milliseconds when fault current exceeds 4–12× the minimum trip rating. For a recloser with 200 A minimum trip, instantaneous pickup between 800 A and 2,400 A balances sensitivity against coordination requirements.

How Coordination Ensures Selective Fault Isolation

Coordination arranges protective devices so only the unit nearest the fault operates, minimizing affected customers. Poor coordination creates two failure modes: upstream devices trip first (blacking out entire feeders for lateral faults), or multiple devices operate simultaneously (extending outage duration and complicating restoration).

Coordination Time Interval Requirements

The coordination time interval (CTI) represents the minimum margin required between device curves. IEEE C37.230 recommends 0.2–0.3 seconds for electromechanical devices, accounting for breaker interrupting time (50–80 ms for modern vacuum units), relay overtravel, and timing tolerances.

Achieving coordination requires analyzing fault current magnitudes at multiple locations. For a typical 15 kV feeder, fault current may range from 8,000 A near the substation to 1,200 A at remote line ends. Each device’s TCC must maintain the required CTI margin across this entire range—curves that cross anywhere within the operating zone indicate coordination failure.

Fuse-Saving vs. Fuse-Clearing Philosophy

Two competing philosophies govern recloser-fuse coordination:

PhilosophyOperationAdvantageDisadvantage
Fuse-savingRecloser fast curve trips before fuse meltsPreserves fuses on temporary faults, reduces truck rollsMomentary outage affects entire feeder
Fuse-clearingFuse blows first, recloser provides backupLimits interruption to faulted lateral onlyHigher fuse replacement cost

Many North American utilities have shifted toward fuse-clearing schemes due to customer sensitivity to momentary interruptions. Power quality metrics like MAIFI (Momentary Average Interruption Frequency Index) increasingly drive protection philosophy decisions.

Time-current coordination plot showing recloser fast and slow curves with fuse minimum melt and total clear curves for fuse-saving coordination
Figure 3. Fuse-recloser coordination on TCC plot. The recloser fast curve must clear faults before the fuse minimum-melt curve across the entire 500–8,000 A operating range. Shaded zone indicates successful fuse-saving coordination with minimum 0.3 s margin.

Sectionalizer Coordination

Sectionalizers have no interrupting rating—they count upstream recloser operations and open during dead time to isolate faulted sections. Settings include shot count (typically 1–3 operations before opening) and reset time (30–90 seconds). This counting-based coordination requires the upstream recloser to complete its full sequence; sectionalizers cannot function with non-reclosing upstream devices.

Ground Fault Settings

Separate ground fault pickup—typically 50–70% of phase pickup—detects unbalanced faults including high-impedance events from downed conductors. Ground elements use longer time delays than phase settings to prevent operation on natural system unbalance. Sensitive ground fault protection can detect currents below 100 A, though coordination with downstream devices becomes increasingly difficult at these levels.


[Expert Insight: Coordination Study Best Practices]

  • Always plot all protective devices on a unified TCC before commissioning—curves that appear coordinated individually may intersect when overlaid
  • Verify coordination at both maximum and minimum fault current levels; curves flatten at lower currents where margins narrow
  • For feeders with distributed generation, reverse fault current can compromise coordination designed for radial power flow
  • Document all settings in a protection coordination database; field changes without documentation create future coordination failures

Step-by-Step Recloser Settings Workflow

Translating coordination principles into actual settings requires systematic analysis. The following workflow applies to most distribution applications, though utility-specific protection philosophies may modify individual steps.

Example: 12.47 kV Overhead Distribution Feeder

StepActionExample ValueRationale
1Obtain maximum fault current from short-circuit study8,200 ADetermines curve operating range
2Determine maximum load current280 APeak feeder demand
3Set phase pickup at 1.5–2× load560 AAvoids cold-load pickup trips
4Select fast curveEI, TMS = 0.05Rapid clearing at high fault currents
5Select slow curveVI, TMS = 0.25Coordinates with downstream 65K fuses
6Define reclose sequence1F-2S-LockoutStandard for overhead feeders
7Set reclose intervals2 s / 25 sAllows arc deionization
8Set ground fault pickup200 A (~70% of phase)Sensitive ground detection
9Plot TCC and verify margins≥0.3 s CTIConfirms coordination across fault range
Nine-step recloser settings workflow flowchart from fault current analysis through TCC coordination verification with example values
Figure 4. Recloser settings workflow for 12.47 kV distribution feeder. Steps 1–2 gather system data; Steps 3–8 configure protection parameters; Step 9 verifies coordination margins before commissioning. Failed verification requires curve adjustment iteration.

When specifying upstream substation breakers, understanding vacuum circuit breaker ratings ensures proper interrupting capacity selection. The substation breaker must handle maximum available fault current while coordinating with all downstream reclosers.

Waiting Time (Reset Time) Configuration

The waiting time parameter—often labeled “W” or “reclaim time”—determines how long the recloser must remain closed before the sequence counter resets. Standard tin-alloy fuse links require 10–30 seconds to dissipate heat after carrying fault current at 200% capacity. Setting waiting time below this cooling threshold risks cumulative thermal damage from successive events.

IEEE C37.60-2019 specifies waiting time ranges from 0.5 to 180 seconds, with most distribution applications requiring 15–45 seconds for proper fuse coordination.

Common Settings Mistakes and Prevention Strategies

Field experience across 200+ recloser installations reveals consistent error patterns. Recognizing these mistakes before commissioning prevents coordination failures and equipment damage.

MistakeConsequencePrevention
Pickup set too lowTrips on transformer inrush (6–10× rated), cold-load pickupSet pickup >1.5× maximum load; verify against inrush calculations
Fast curve too slowFuse melts before recloser—defeats fuse-saving schemePlot TCC; confirm fast curve clears ≥0.1 s before fuse minimum-melt
Reclose interval too shortArc not deionized, immediate re-trip on temporary faultMinimum 0.3 s for vacuum interrupters; 1–2 s for overhead lines
Ground settings ignoredHigh-impedance faults (downed conductor) undetectedSet sensitive ground pickup with extended time delay
No coordination studyProtection misoperation, device race conditionsPlot all devices on unified TCC before energizing
Waiting time too shortCumulative fuse damage from repeated fault eventsSet ≥15 seconds minimum for fuse coordination

For outdoor distribution applications requiring pole-mounted protection with configurable settings, the ZW32 outdoor vacuum circuit breaker series supports multiple curve families and sequence configurations through integrated microprocessor controls.

Selecting Reliable Switchgear for Protection Schemes

Protection performance ultimately depends on hardware quality. Vacuum interrupter integrity determines interrupting reliability, control electronics accuracy governs pickup and timing precision, and communication capability enables remote settings adjustment and fault data retrieval.

Modern reclosers integrate with SCADA systems using DNP3 or IEC 61850 protocols, supporting remote curve changes and automated fault location. This connectivity eliminates truck rolls for routine settings adjustments while providing real-time fault data for coordination verification.

Selecting equipment from manufacturers with protection engineering expertise ensures application support from specification through commissioning. XBRELE supplies vacuum interrupter-based switchgear with factory-configurable protection settings and coordination analysis support for utilities and industrial customers. Contact our engineering team for application assistance.


Frequently Asked Questions

What is the difference between a recloser and a standard circuit breaker?
A recloser automatically tests whether faults have cleared by reclosing after tripping, while standard circuit breakers remain open until manually reset or remotely commanded. Reclosers typically execute 2–4 operations before locking out, making them suited for overhead lines where 70–90% of faults are temporary.

How do I determine the correct pickup current setting?
Set phase pickup at 1.5–2× maximum expected load current to avoid trips during cold-load pickup or motor starting. For a feeder with 300 A peak demand, pickup between 450–600 A provides adequate margin while maintaining fault sensitivity.

Why would a recloser lock out on what appears to be a temporary fault?
Common causes include reclose intervals too short for complete arc deionization, pickup settings too sensitive for inrush conditions, or the fault actually persisting longer than expected. Review fault current magnitude from event records to determine whether the fault exceeded temporary event characteristics.

What coordination margin should I maintain between devices?
IEEE C37.230 recommends 0.2–0.3 seconds minimum coordination time interval between adjacent protective devices. This margin accounts for breaker interrupting time, relay timing tolerances, and measurement uncertainty. Verify margins at both maximum and minimum fault current levels.

Can recloser settings be changed without physical access to the unit?
Yes, modern microprocessor-based reclosers support remote settings changes via SCADA or dedicated communication protocols. Remote capability requires proper cybersecurity measures and change management procedures to prevent unauthorized modifications.

How does altitude affect recloser settings?
Altitude above 1,000 meters reduces air density and dielectric strength, potentially requiring derating of interrupting capacity. Settings themselves remain unchanged, but the recloser’s physical capability to interrupt fault current decreases approximately 1% per 100 meters above 1,000 meters according to IEEE C37.60.

When should I use fuse-saving versus fuse-clearing coordination?
Fuse-saving reduces maintenance costs by preserving fuses during temporary faults but causes momentary interruptions across the entire feeder. Fuse-clearing limits interruptions to the faulted lateral but increases fuse replacement frequency. The choice depends on utility power quality priorities and customer sensitivity to momentary events.

Hannah Zhu marketing director of XBRELE
Hannah

Hannah is the Administrator and Technical Content Coordinator at XBRELE. She oversees website structure, product documentation, and blog content across MV/HV switchgear, vacuum breakers, contactors, interrupters, and transformers. Her focus is delivering clear, reliable, and engineer-friendly information to support global customers in making confident technical and procurement decisions.

Articles: 99