Solicite un presupuesto para componentes y equipos de alta tensión

Indíquenos sus requisitos (tensión nominal, modelo, cantidad y destino) y nuestro equipo de XBR Electric le preparará un presupuesto detallado en un plazo de 24 horas.
Formulario de contacto Demo
Technical illustration of a medium-voltage vacuum contactor FAT and SAT acceptance matrix with test checkpoints and inspection callouts

Vacuum Contactor FAT/SAT Acceptance Matrix Guide

A vacuum contactor FAT/SAT acceptance matrix is the structured, line-by-line document that records every verification activity performed on a vacuum contactor — first at the manufacturer’s facility (Factory Acceptance Test) and then at the installation site (Site Acceptance Test) — along with the specific pass/fail threshold, the responsible party, and the authorized sign-off for each item.

This guide covers what the matrix must include, how to evaluate supplier submissions, and what a complete handover package requires — from purchase specification through final sign-off.

Overview diagram of a vacuum contactor FAT and SAT acceptance matrix with documentation, electrical, mechanical, vacuum, and sign-off stages
A complete FAT/SAT matrix tracks each verification item from documentation review through final sign-off.

Quick Diagnosis: Common FAT/SAT Failure Modes

SíntomaPrimera pruebaCausa probablePróxima acción
Insulation resistance below 100 Mohm at FATRe-test after 30-min dry-out at 40 deg CMoisture ingress or contaminated interrupterInvestigate gland seals and enclosure integrity; replace interrupter if IR does not recover
Hi-pot leakage current spikeReduce voltage; re-apply slowlyCracked vacuum interrupter or inadequate creepageReplace interrupter; do not re-test without root-cause resolution
One contact resistance pole 2-5x higher than othersVerify contact spring force with go/no-go gaugeUneven contact wear, misalignment, or contaminated surfaceDisassemble, inspect contact faces, re-test
Contactor fails to close at 85% rated coil voltageMeasure voltage at coil terminals, not panel supplyUndersized control cable causing voltage dropReplace control cable to specified cross-section; re-measure
Pole-to-pole operating time asymmetry > 3 msCheck mechanism alignment with manufacturer toolingMechanical binding or worn pivotRealign mechanism; re-test timing
Audible re-strike after load interruption at SATVacuum integrity hi-pot across open contactsDegraded vacuum in interrupterReplace interrupter; do not re-energize
B-phase lug temperature 20+ deg C above A and CMicro-ohmmeter on B-phase terminationUnder-torqued or incorrectly re-made connectionRe-torque to specification; repeat thermographic scan after 30-min run

What the Acceptance Matrix Must Cover

At its most precise, the acceptance matrix is a tabular record structured around four columns: the specific test or document item, the acceptance criterion derived from IEC 62271-106 or ANSI/IEEE C37.66 or the project specification, the actual measured result (not a checkbox), and a dated signature from the inspector or commissioning engineer.

  1. Documentation verification — type test certificates, routine test reports, vacuum integrity certificates, and drawing packages matched to the serial number under test.
  2. Dielectric and insulation tests — power-frequency withstand, partial discharge measurement, and insulation resistance referenced to the rated voltage class and ambient temperature.

Documents Required Before Testing Can Begin

Missing documentation is the most common reason FAT sessions are delayed or invalidated. The table below maps each required document to its owner, the stage at which it must be available, and the consequence of absence.

DocumentoOwnerRequired AtRisk If Missing
Approved single-line and schematic drawingsSupplierFAT startCannot verify wiring against design intent
Vacuum contactor datasheet (rated voltage, current, BIL, endurance class)SupplierFAT startNo baseline for electrical test limits
Bill of Materials with part numbers and revisionSupplierFAT startCannot confirm correct components were installed
Type-test certificates (IEC 62271-106 or equivalent)SupplierFAT startNo evidence that design class was ever validated
Calibration certificates for all test instrumentsBuyer / Test LabFAT startTest results are inadmissible without traceable calibration
Factory test procedure with acceptance limitsSupplierFAT startNo agreed pass/fail criteria; disputes likely
Insulation coordination studyBuyer / EngineerFAT startCannot confirm BIL and clearance choices are site-appropriate
Site specification / purchase order technical annexBuyerFAT startSupplier may test to generic standard, not project requirements
Packing and shipping specificationSupplierFAT endNeeded to verify contactor survives transit before SAT
Site survey data (altitude, ambient temp, humidity, pollution degree)BuyerSAT startCannot apply derating factors or confirm installation class
Installation and commissioning manualSupplierSAT startNo reference for torque values, clearances, or interlock checks
Transport and storage inspection recordBuyer / LogisticsSAT startNo evidence of condition between FAT and site arrival
As-built drawings (post-FAT revision)SupplierSAT startSAT wiring checks reference pre-FAT drawings, not actual hardware
FAT sign-off reportBuyer + SupplierSAT startSAT cannot begin on equipment with no accepted FAT record

Electrical and Mechanical Tests Required at Factory Acceptance

Every measurement taken during FAT becomes a reference point for SAT comparison and future maintenance benchmarks.

Pruebas eléctricas

Hi-Pot Dielectric Withstand

Tensión nominal (kV)AC Hi-Pot Level (kV rms, 1 min)DC Hi-Pot Level (kV)
<= 3.61014
7.22028
122840
17.53854

Vacuum Integrity Test

Contactor RatingTypical Acceptable Contact Resistance
Up to 400 A<= 100 micro-ohm per pole
400 A – 800 A<= 60 micro-ohm per pole
> 800 APer manufacturer’s datasheet

Mechanical Tests

ParámetroTypical Acceptable Range
Contact gap (12 kV class)8-12 mm per pole
Toallita de contacto2-4 mm per pole
Pole-to-pole gap variation<= 1 mm
Factory test illustration showing hi-pot testing, contact resistance measurement, timing analysis, and contact gap inspection on a vacuum contactor
FAT benchmarks establish the baseline for dielectric, resistance, timing, and mechanical acceptance.

FAT Test Summary

PruebaStandard ReferenceCriterio de aprobaciónFailure Action
Hi-pot dielectric withstandIEC 62271-106No breakdown; leakage < limitReplace interrupter; investigate insulation
Integridad del vacíoIEC 62271-106 / manufacturer specNo gap breakdown; pressure < 10^-3 PaReplace interrupter before shipment
Resistencia de contactoIEC 62271-1Within limit; poles within 10% of each otherInspect contacts; verify spring force
Resistencia del aislamientoIEC 60060-1>= 1,000 Mohm at 1 kVInvestigate moisture or contamination
Coil pickup/drop-out voltageManufacturer specCloses at 85%; opens at <= 75% ratedAdjust or replace coil assembly
Mechanical endurance cyclingIEC 62271-106No failure in 50-100 cyclesIdentify binding point; re-test
Operating timeManufacturer specWithin +/-15% of baseline; pole asymmetry <= 3 msRealign mechanism
Contact wipe and gapManufacturer specWithin dimensional toleranceAdjust mechanism; re-measure

Tools and Acceptance Sources Reference

Instrumento / FuentePropósitoReferencia de aceptación
DC micro-ohmmeter (>= 100 A injection)Medición de la resistencia de contactoManufacturer datasheet; IEC 62271-1
1 kV / 2.5 kV megohmmeterResistencia del aislamientoIEC 60060-1; project specification
AC hi-pot test set (calibrated)Dielectric withstandIEC 62271-106 voltage tables
Contact timing analyzerClose and open time measurementManufacturer spec; +/-15% of FAT baseline
Llave dinamométrica calibradaTerminal and busbar connection torqueManufacturer installation manual
Feeler gauge / manufacturer go/no-go toolingContact gap and wipeManufacturer dimensional spec
Infrared thermometer / thermal cameraTermination temperature rise during loaded SATIEC 60529 / project thermal limits
Power quality analyzer or oscilloscopeInrush current capture at first load energizationProject protection coordination study
Relay test setEnd-to-end protection trip injectionProject relay settings schedule
OEM installation and commissioning manualTorque values, clearances, interlock sequencesManufacturer document
Project specification / purchase order technical annexSite-specific acceptance thresholdsBuyer-issued document
IEC 62271-106FAT/SAT test levels and proceduresIEC (current edition)
ANSI/IEEE C37.66Vacuum contactor requirements (North American projects)IEEE (current edition)

Site Acceptance Testing: Structure and Field Scenario

SAT confirms that a vacuum contactor performs correctly within its actual installed environment, validating integration: cabling, control voltage levels, upstream protection coordination, enclosure thermal behavior, and specific load characteristics.

Stage 1 — Pre-Energization Checks (de-energized, locked out)
Stage 2 — Control Power and Functional Verification

Field Scenario: 6.6 kV Contactor at a Coastal Pump Station MCC

Site acceptance inspection scene with vacuum contactor in MCC, technician checks coil voltage, thermal scan, and cable terminations
SAT reveals installation issues such as voltage drop, moisture ingress, and hot terminations that FAT cannot catch.

How to Evaluate and Compare Supplier FAT/SAT Matrix Completeness

Score each supplier’s submission against the criteria below. Assign points only when verifiable evidence — test records, calibration certificates, sign-off sheets — is attached.

Evaluation CategoryMax PointsWhat Earns Full ScoreCommon Shortfall
Dielectric and insulation tests20Hi-pot at rated voltage plus BIL impulse, individual serial numbers logged, pass/fail limits statedHi-pot performed on batch sample only; no per-unit record
Contact gap and travel measurement15Gap measured with calibrated gauge, travel curve plotted, min/max limits per specGap stated as “within tolerance” with no numerical result
Verificación de la integridad del vacío15Hi-pot or power-frequency withstand across open contacts per IEC 62271-106; dated result per unitVacuum integrity assumed from factory date code; no test performed
Coil operate/release voltage10Tested at 85% and 110% of rated control voltage at actual site ambient temperatureTested only at nominal voltage in conditioned lab
Mechanical endurance sample10Cycle count documented with minimum threshold stated; spring force verified post-testEndurance data from type-test report only; not from production batch
Environmental condition logging10Ambient temperature, humidity, altitude, and vibration recorded at time of each SAT testSAT forms lack environmental data fields
Calibration traceability10All instruments traceable to national standard; calibration due dates visible on certificatesCalibration stickers present but expiry dates not checked against test date
Sign-off chain completeness10Manufacturer, independent inspector, and client representative signatures on each test recordClient sign-off blank or obtained after energization
Non-conformance handling5Out-of-tolerance results documented with disposition: rework, retest, or accept-with-deviationNC events absent from record (statistically implausible for large orders)
Revision and change control5Matrix version number, revision history, and applicability to specific purchase order referencedGeneric template with no project-specific identification
Total110

Interpretation:
– 95-110 points: Matrix is substantially complete. Proceed to contract with minor clarification requests.


Sign-off Criteria and Handover Record Requirements

Final acceptance converts a tested contactor into a commissioned asset. Without a defined sign-off protocol, test data loses its traceability value.

Witness Levels

Witness LevelDefiniciónFunción típica
W — WitnessHold point; work stops until authorized witness signsOwner’s engineer, third-party inspector
R — ReviewRecord reviewed and approved before next stageEngineering manager, QA lead
I — InformationCopy filed; no hold requiredSite commissioning team

Mandatory Handover Documents

DocumentoContent RequiredSign-off Authority
FAT test reportAll factory test results, instrument calibration certificates, NCR log with dispositionsManufacturer QA + witness engineer
SAT commissioning recordSite test results mapped to FAT baseline, as-installed wiring diagramsSite commissioning lead + owner’s engineer
Non-conformance report logEvery deviation raised, corrective action taken, re-test result, closure signatureQA manager
Instrument calibration registerCertificate reference, expiry date, and traceability standard for every instrument usedTest supervisor
Insulation resistance baseline recordPhase-to-phase and phase-to-earth IR values at handover, for future maintenance trendingCommissioning lead
Contact resistance baseline recordPer-phase resistance values at handoverCommissioning lead
Operating time recordClose and open time measurements at handoverCommissioning lead
As-built drawing packageFinal single-line, control schematic, terminal scheduleEngineering lead
Warranty activation formSerial numbers, factory test date, SAT completion date, warranty period startOwner’s contract manager
Handover documentation diagram for vacuum contactor FAT SAT sign-off including reports, calibration records, as-built drawings, and warranty activation
Final acceptance depends on signed test records, calibration traceability, and a complete handover package.

Procurement Checklist: Specifying a Compliant FAT/SAT Package

Use this checklist before issuing a purchase order or inviting a vendor to bid.

  • Rated voltage, current, and switching duty cycle are defined and matched to the contactor’s published vacuum interrupter ratings.
  • Dielectric withstand levels (power frequency and impulse) are stated and reference the applicable IEC or ANSI/IEEE standard.

Referencias de ingeniería XBRELE relacionadas

Utilice estas referencias XBRELE para conectar la decisión de campo con el producto correcto, la prueba y el flujo de trabajo de adquisición: Página del producto XBRELE, Gama de disyuntores de vacío XBRELE, Guía de calificaciones del VCB, Lista de comprobación para la aceptación del FAT/SAT de VCB, XBRELE vacuum contactor range.

Contexto normativo

Para el contexto del método externo, compare el procedimiento del sitio con el público Página de normas IEEE C37.09 y, a continuación, aplicar el manual exacto del OEM y las especificaciones del proyecto para el equipo suministrado.

Ejemplo de campo

Ejemplo práctico: durante una inspección de servicio, una fase midió fuera de su línea de base de puesta en servicio, mientras que las otras dos fases se mantuvieron estables. El equipo repitió la medición con cables verificados, comprobó la temporización y el recorrido de los contactos y utilizó la divergencia medida para separar un problema de presión de contacto de un problema genérico de limpieza de superficies.

Preguntas frecuentes

What is the difference between FAT and SAT for a vacuum contactor?

FAT (Factory Acceptance Test) verifies that the contactor meets design and manufacturing requirements before it leaves the supplier’s facility. SAT (Site Acceptance Test) verifies that the same unit arrived undamaged, was installed correctly, and performs within tolerance under actual site conditions — supply voltage, ambient temperature, altitude, and connected load.

Which IEC standard governs vacuum contactor FAT and SAT requirements?

IEC 62271-106 is the primary standard for alternating current contactors for voltages above 1 kV. It defines routine test requirements (performed on every unit), type test requirements (performed on a design sample), and the test levels for dielectric withstand, vacuum integrity, and mechanical endurance.

How do I verify vacuum integrity at site if I do not have a vacuum gauge?

The standard site method is a power-frequency withstand test applied across the open contact gap of each interrupter. If the gap holds the specified voltage without breakdown, the vacuum is adequate.

What contact resistance value should I expect from a new vacuum contactor?

For contactors rated up to 400 A, a typical acceptable value is <= 100 micro-ohm per pole measured with a DC micro-ohmmeter injecting at least 100 A. For 400 A to 800 A ratings, <= 60 micro-ohm per pole is a common threshold.

Can SAT be waived if the contactor passed a comprehensive FAT?

No. FAT and SAT address different risk categories.

How long should FAT and SAT records be retained?

Retain records for the service life of the equipment plus the period required by applicable regulations. For medium-voltage switchgear, 10 years minimum is a common requirement, but some jurisdictions and industries (utilities, nuclear, petrochemical) require longer retention periods.

What should I do if a supplier submits a FAT report with no non-conformance entries on a large order?

Treat it as a quality system concern, not a positive result. A zero non-conformance record across more than 10 units is statistically implausible if the matrix was applied rigorously.

Hannah Zhu, directora de marketing de XBRELE
Hannah

Hannah es administradora y coordinadora de contenido técnico en XBRELE. Supervisa la estructura del sitio web, la documentación de los productos y el contenido del blog sobre aparatos de conexión de media y alta tensión, interruptores de vacío, contactores, interruptores y transformadores. Su objetivo es proporcionar información clara, fiable y fácil de entender para los ingenieros, con el fin de ayudar a los clientes de todo el mundo a tomar decisiones técnicas y de adquisición con confianza.

Artículos: 156